10/30/2006 29th Street work begins to gain access to the property
1/15/2007 Inside PUD road work begins
2/15/2007 First home building permit submitted for approval by the City
4/2/2007 We begin to frame the first home!
4/24/2007 Second home started
5/07/2007 Third home started
5/21/2007 Website updated with a new siteplan map for this project
7/2/2007 Phase 1 plat all signed off and recorded
7/9/2007 First home prices set: $198,500
Sept 2007 First person moves into her new home! 2 more homes under agreement.
10/6/2007 We are part of the Enviro Home tour
11/10/2007 Four homes, of the 11 available in phase 2, are on 'hold' for certain people
11/11/2007 First phase of homes (first 7) are sold, we now wait on paperwork with City before selling phase 2
3/17/2008 Paperwork with City complete! We can start selling the remaining 11 homes (6 on hold, 5 remaining to sell)
8/15/2008 Last home in the project is under agreement, sale pending 9/15/08
10/1/2008 Project Complete - thank you everyone!